You order material with a buffer, just in case, and yet two or three times a month production stops because a single screw or a sheet of a specific thickness is missing. The warehouse swells with components that have been sitting for half a year, while at the same time someone regularly calls the supplier to ask for an express delivery. This is not a problem of people planning badly. It is a signal that an MRP system for a small company has stopped being textbook theory and become a question about real money that today sits locked inside an Excel spreadsheet. In this article we show how to recognize that moment and what a minimal MRP looks like, without the inflated theory.
Signs that planning materials in Excel is already costing you
Excel copes brilliantly as long as a company has a dozen or so material items and a handful of jobs in progress. The problem grows slowly, so it is easy to miss until someone actually counts how much it really costs.
- Production stops for lack of material even though the warehouse “should” have stock. The spreadsheet shows the level from a week ago, not from an hour ago. The gap between “should be” and “is” usually comes down to a forgotten consumption, a return, or a parallel tab that someone did not update.
- Emergency orders from a supplier happen more often than once a month. An express delivery usually costs more than a standard one, sometimes markedly more. If this keeps repeating, you are paying a permanent premium for the lack of planning, not a one-off mishap.
- Material sits in the warehouse that no one has used for several months. That is frozen cash, bought with a buffer because no one was sure how much is really needed for the jobs in the queue.
- Preparing the requirements for the coming week takes one person half a day. That person copies data across several tabs, checks open orders, and calls the warehouse to confirm stock levels. This is time that creates no value beyond the copying itself.
- The MRP spreadsheet in Excel lives in one person’s head. Only one planner understands the formulas, and their holiday or departure from the company means a week of chaos in ordering.
- No one can quickly answer how much material to order for a new job. The answer is “let me check and call you back”, because the data on stock levels, orders in transit, and planned production sits in three different places.
Each of these signs on its own looks like a minor inconvenience. Together they mean that the cost of keeping planning in a spreadsheet has exceeded the cost of deploying a system that does the same thing automatically.
MRP, what it actually is, without the encyclopedia
MRP, that is Material Requirements Planning, is a method that answers three questions for every material and component in the company: what, how much, and when to order so that planned production runs without stoppages and without excess stock. That is all. Everything else is details of execution.
The three questions MRP answers
First: what is needed. Based on the product structure (the BOM, that is the list of materials and components), the system breaks a production order down into specific items, not into a general product name.
Second: how much is needed. The system calculates gross requirements from the production plan, subtracts what is already in stock and what is in transit, and leaves the net requirement, that is the real quantity to order.
Third: when to order. Knowing the supplier’s lead time, the system counts backwards from the date the material is needed and points to the day on which the order has to go out so that the material arrives on time.
Why a spreadsheet copes with this worse and worse
Excel can calculate the same thing as long as the number of material items, levels of the product structure, and open jobs stays small. Every extra BOM level, that is a subassembly made of other subassemblies, multiplies the number of formulas and cross-references between tabs. At some point a single supplier price change or a single quantity change in an order requires manually recalculating a dozen or so cells across several files at once. An error is easy to enter and hard to catch, because the spreadsheet does not warn you that something is inconsistent. It gets caught only when material runs out on the shop floor.
What a minimal MRP looks like in a small company
A minimal MRP does not mean a full APS-class system with minute-by-minute scheduling on every machine. For a company employing 10 to 50 people, a sensible starting point is far narrower.
The four elements without which MRP will not work
- Product structures (BOMs) for products that actually recur. You do not have to map out every historical variant, just what genuinely goes into production in the coming months.
- One, up-to-date stock level. Not three spreadsheets updated at different rhythms, but a single source of truth, visible at once to the warehouse, purchasing, and production.
- A production plan a few weeks ahead. Even a simplified one, based on accepted orders and typical lead times, is enough as a basis for calculating requirements.
- Lead times from your key suppliers. Without them the system cannot work out when an order has to go out, and that is exactly the difference between planning and guessing.
What you do not need at the start
At the start you do not need hour-by-hour scheduling at every workstation, automatic supplier selection based on optimization algorithms, or a demand-forecasting module built on machine learning. All of that can be added later, if the company grows and genuinely needs it. At the start what matters is that the four elements above live in one place and update automatically, not by hand.
| Area | Planning in Excel | Minimal MRP in a system |
|---|---|---|
| Stock level | Updated by hand, usually with a delay | Updates automatically on every issue and receipt |
| Net requirement | Calculated by hand for each order separately | Calculated automatically from the BOM and production plan |
| Order date | Set by eye or from the planner’s memory | Computed backwards from the need date and the lead time |
| Visibility for the team | One file on one computer, often one person’s | A shared data source for purchasing, the warehouse, and production |
| Risk of error | Grows with every extra level of the product structure | The system keeps the formulas and calculations consistent on its own |
From spreadsheet to system: how to start without overdoing it
Do not start by choosing a system. Start by counting what planning in a spreadsheet costs you today: the planner’s hours, the cost of emergency orders, the value of stock that does not turn over. Only that number shows whether deploying a minimal MRP is worth it at all at your scale. In many manufacturing companies employing 10 to 50 people, these three costs together can exceed the cost of launching an MRP module in an ERP system within the first year.
MRP on its own rarely lives as a separate application, because it needs data about the warehouse, orders, and product structure, so it naturally runs as a module within a wider ERP system. We write more about what that approach looks like across the whole shop floor on our ERP for manufacturing page. You will find other articles on the next steps of digitizing production on our blog.
Our Digital Growth Diagnosis measures, among other things, exactly these three costs in the area of inventory and production, so before you ask a vendor for the price of an MRP module, it is worth knowing how much this problem really costs you today. We have worked with Odoo since 2011, with clients in three countries, Poland, Germany, and Belgium.
Frequently asked questions
How does MRP differ from an ordinary purchasing plan in Excel?
A purchasing plan in Excel rests on what someone entered and updated by hand. MRP calculates requirements automatically from the product structure, the current stock level, and the production plan, so the result is as current as the data in the system, not as the last update of the spreadsheet. The difference grows with the number of material items and jobs in progress.
Does a small company employing 10-20 people even need MRP?
The need does not depend on the number of employees, only on the number of material items and levels of the product structure. A company with a simple, single-level product can comfortably stay with a well-built spreadsheet for longer. A company whose product is made of subassemblies built from other subassemblies usually feels the limits of Excel at a dozen or so open jobs at once.
Do you have to deploy a whole ERP to have working MRP?
MRP needs data that usually lives in an ERP system anyway: the warehouse, orders, and product structure. You can start narrower, with just the warehouse and production module, but in practice it is hard to have sensible MRP without that data in one place. That is why it makes more sense to talk about deploying an MRP module within a system, rather than a separate application glued onto the rest of the processes.
How long does launching a minimal MRP take?
It depends mainly on the state of the input data, not on the system itself. If the product structures and material records are already tidy, configuring the module takes little time. What usually eats the most time is cleaning up data that has lived for years across several versions of a spreadsheet, with duplicates and missing units of measure.
Before you decide whether you need MRP, run a simple self-check. Count how many times in the last month production stopped for lack of material, how much the emergency orders cost, and how many hours someone spent preparing requirements in Excel. If the total is striking, our Digital Growth Diagnosis will show exactly where in your material planning process the biggest cost sits, before you pay for any system at all.