The decision is already made: Excel on the shop floor stopped being enough, and Comarch Optima can no longer keep up with orders, inventory and planning. One question is left, and it blocks everything: what happens to the data. Migrating from Comarch Optima to a new ERP system carries the fear that the invoice history will vanish, that the accountant will be left with no view of the previous year, that the company will stop issuing documents for a week. That fear is legitimate, but it can be managed methodically instead of becoming a reason to freeze. Below we show what the move from Optima really looks like, how long it takes and exactly what happens to each type of data along the way.
The biggest fear: that something disappears along the way
The owners of manufacturing companies we talk to about changing their ERP system almost always start with the same sentence: "we have ten years of history in Optima, we cannot lose that". They are right that the stakes are high, but they are wrong that migration inherently risks losing data. Data loss is the result of a bad migration process, not an unavoidable stage of changing systems.
A well run migration never means flipping the production system overnight with no safety net. The old system stays active and available for reference throughout the process, the data is exported and verified in a test environment, and the switch to the new system happens only once the numbers match: stock levels, customer balances, document history. Only after that verification does Optima stop being the company's operating system and become an archive for reference.
What can actually be exported from Comarch Optima
In practice, a Comarch data export covers all the key records that make up the company's daily work. The scope we most often migrate when moving from Optima to Odoo:
- Customer and supplier records: company details, addresses, payment terms, history of cooperation.
- Product and service records: item codes, units of measure, prices, product groups.
- Sales and purchase documents: invoices, corrections, orders, with the historical numbering preserved.
- Stock levels as of the cutoff date, together with locations and lots, if the company tracks them.
- Accounts receivable and payable balances: what is paid, what is open, as of which date.
How smoothly the export goes depends largely on how well organised the data in Optima is today. A company that ran its product records for years without discipline (duplicate item codes, missing units of measure, inconsistent naming) will not get a worse migration simply because it changes systems, but it will get more work at the data cleaning stage, before anything even reaches the new system. That is why every serious ERP change project starts with an audit of the current state of the data, not straight away with configuration.
The migration stages step by step
The move from Optima to Odoo has a repeatable structure, regardless of company size. Below is the order in which we actually run such a project:
- Audit of the source data: what is in Optima, what condition it is in, what needs cleaning before export.
- Comarch data export: records, documents and balances pulled out in formats that can be mapped to the structure of the new system.
- Cleaning and mapping: removing duplicates, standardising units of measure and codes, assigning Optima fields to their matching fields in Odoo.
- Import into a test environment: the data goes into a copy of the system invisible to customers and suppliers, where it can be checked safely.
- Consistency check: comparing balances, stock levels and document counts between the old and the new system, item by item where possible.
- Training the team on the company's real, already imported data, not on sample demo records.
- A short period of both systems running in parallel, during which Optima stays available for reference while the new system takes over day to day operations.
- Cutover and go live support during the first weeks of normal work on the new system.
| Stage | What happens | Approximate time |
|---|---|---|
| Audit of the source data | Review of records and documents in Optima, assessment of data quality | A few business days |
| Data export and cleaning | Pulling the data out of Optima, removing duplicates, mapping fields | 1 to 2 weeks |
| Test import and verification | Data in the Odoo test environment, comparison of balances and stock levels | A few days to a week |
| Team training | Working on the company's real, already imported data | In parallel with the previous stage |
| Parallel run and cutover | Optima available for reference, the new system takes over daily work | Usually 1 to 2 weeks |
How long does migration from Optima to Odoo take
The honest answer: it depends above all on the quality of the source data and on how broad a range of processes the new system takes over, not on the import technology itself. A company with tidy product records and a simple scope (sales, inventory, basic accounting) goes through this process faster than a company with a complex, multi level BOM and years of backlog in tidying up its data.
We have a reference point for this from our own history. Our first client, whose name we do not disclose, received a working demo of the system the day after the first conversation, and we launched the full production system two weeks later. That company was later acquired by a German listed group, and the same core of the system still runs there today. We do not promise every client exactly two weeks, because every company's scope is different, but this story shows that pace is not a limitation of the platform: Odoo lets you show a working system very quickly, and the real duration of the whole project depends mainly on the state of the data on the client's side and the pace of decisions, not on the technical capabilities of the implementer.
Accounting continuity: what happens to the current month
The second most common fear, alongside data loss, is a break in accounting continuity: the worry that during the system change the company will no longer be able to issue invoices or will lose track of the month's settlement. Good practice when changing an ERP system is to plan the switch at the boundary of an accounting period, most often the end of a month or quarter, so that the accountant closes one period in Optima and starts the next one already in the new system with clean opening balances. Optima does not disappear in the meantime, it stays available for reference for audits and historical reports.
The same moment of changing systems is worth using to get invoicing ready for KSeF. From 1 February 2026 every taxpayer must be able to receive invoices in KSeF, and from 1 April 2026 the obligation to issue invoices in KSeF covers practically all B2B turnover, while for the smallest companies, with gross sales up to PLN 10,000 per month, only from 1 January 2027. A company that has to adapt its invoicing process anyway often goes through this change more cheaply and with less chaos together with the system migration than by running two separate projects a few months apart.
Frequently asked questions
Will I lose access to old invoices from Optima after migration?
No. Optima stays available for reference after the migration is complete, precisely in order to keep continuous access to historical documents. The migration moves the current operating data and the history needed to work in the new system, but it does not delete the old system overnight.
Can you migrate during the tax year?
Yes, although it is more convenient to plan the switch at the boundary of an accounting period, usually the end of a month or quarter. That lets you close one period in the old system and start the next one in the new system with a clean, verified opening balance, instead of splitting a single accounting month between two systems.
Who is responsible for the correctness of the data after migration?
Responsibility is shared. The implementation company is responsible for the technical side of export, mapping and import, and for verifying that balances and stock levels match. The client is responsible for the quality of the source data: what has been inconsistent in Optima for years will not become consistent just because it is moved to a new system. That is why the data audit at the start of the project is a mandatory stage, not an optional one.
Will the migration halt current invoicing?
A well planned migration does not stop the company's work. Optima handles current invoicing until the cutover, and the switch is planned at the boundary of an accounting period to avoid a gap in issuing documents. The short period of both systems running in parallel exists precisely so that the team can adjust without any risk to sales continuity.
Before you start exporting data from Comarch Optima, check whether changing systems will actually solve your bottleneck. The Digital Growth Diagnosis is an audit of 39 KPIs across 7 dimensions that shows where the company loses money and whether the priority is migrating from Optima or rather tidying up the processes around the system you already have. We have worked with Odoo since 2011, for clients in three countries: Poland, Germany and Belgium. You will find more comparisons and implementation stories on our blog.